Phase 1

SHIFT Phase 1 Schedule
  • October 2022 to June 2024

 

AiM Operations and Maintenance

Additional Timeline Image - Information is provided in text
  • Initial Training - October to November 2022
  • Future State Design - December 2022 to March 2023
  • Data Migration - January to April 2023
  • System Setup - March to April 2023
  • Workflow Walkthrough & System Setup - May to September 2023
  • Integrations & SDC Testing - March 2023 to January 2024
  • End to End Testing - January to March 2024
  • Training -April to May 2024
  • Go-Live Activities - May to June 2024

 

AiM Space and Property Management

Additional Timeline Image - Information is provided in text
  • AssetWorks Project Management Planning - February 2023
  • Implementation Planning - March 2023
  • Initial Training - March 2023
  • Future State Design - April to June 2023
  • Data Migration - June to July 2023
  • Workflows & System Setup - July to September 2023
  • Training - September to November 2023
  • AiMCAD - July to December 2023
  • Go Live - June 2024

 

ReADY Request

Additional Timeline Image - Information is provided in text
  • AssetWorks Project Management Planning - April to May 2023
  • Initial Training - April to May 2023
  • Template Design & Testing - May to October 2023
  • Documentation & Testing - November to December 2023
  • Training - December 2023
  • Go Live - June 2024

 

AiM Keys and Access Control

Additional Timeline Image - Information is provided in text
  • AssetWorks Project Management Planning - July to August 2023
  • Initial Training - August 2023
  • Future State Design - August to September 2023
  • Data Migration - August to September 2023
  • Workflow Walkthrough - September to October 2023
  • Training - October to November 2023
  • Go Live - June 2024

 

Phase 2

Image of Phase 2 Timeline - Information is provided in text
  • Targeted to begin Summer/Fall 2024